Orbital Welding Used on Hondo's Firewater System
Orbital Welding Used on Hondo's Firewater System
Replacement of the firewater
system on the Hondo Platform in the Santa Barbara Channel off the coast of
southern California required fabrication of a piping system incorporating the
latest concepts in material selection, metal fabrication, and joining
technology. Previous success with use of thin-walled, copper-nickel pipe
provided superior corrosion resistance in a marine environment compared to
carbon steel.
Orbital welding was evaluated as an alternate joining method. Coupons of 6-in.
and 3-in. copper-nickel pipe were welded using orbital welding equipment.
Examination and testing showed the welds to be of excellent quality.
Copper-nickel is a difficult material to weld by hand. Results of initial
qualification welding tests showed only two of the eight manual welding
candidates passed. This was an additional incentive to use the orbital welding
equipment.
The firewater system fabricated is the seawater distribution system supplying
deluge spray nozzles at various points on the platform. The complete firewater
system consists of the firewater manifold system of 10-in. pipe that
distributes water to the smaller diameter pipe and ultimately to the sprinkler
heads located in a total of 11 zones or areas.
The project required 9,000 ft of pipe of all sizes up to 10 in. and would need
3,140 welds. Piping of two in. and under was to be joined by threaded fittings.
While most of the butt welds could be done with the orbital equipment, some
welds, such as welding the weld-o-lets and thread-o-lets to the pipe, were weld
joints that were not practical to weld by machine. These were done manually.
Harmony Construction networked with other companies in order to find skilled
manual welders that could do the required manual welds on copper-nickel, and
who would be capable of learning to operate the orbital pipe welding equipment
within the specified time.
Procedure development
Equipment had to be obtained and the operators trained in its use. A Model 215
microprocessor-controlled pipe welder power supply and a Model 15 weld head
were obtained from Arc Machines. Six days were spent training the experienced
hand welders on the use of the orbital equipment.
Preliminary weld program development was done so the operators could become
familiar with the travel speed, welding currents, arc voltage control,
pulsation rate, wire feed rate, and oscillation of the torch across the weld
joint. Operators are able to make adjustments in these parameters within
prespecified limits during welding and to make minor adjustments in steering
the torch as required.
The weld programs, with all of the parameters specified for a particular size
of pipe, are entered into the power supply memory via the Model 215 Program
Operator Pendant. In order to weld that size again, the program number is
recalled and the exact same parameters are executed with allowances for
overrides as specified.
When the operators were comfortable in setting up and operating the equipment,
the task of developing welding schedules for production welding of each size of
pipe began. The welding crew started with the 6-in. pipe with a 0.134-in. wall,
followed by smaller sizes. The training and the procedures for every size
except the 10-in. pipe were completed. The 10-in. pipe, which was the most
challenging, was done last.
The 10-in. pipe was for the firewater manifold system. It had a wall thickness
of 0.187-in. and required the same J-bevel preparation used on the smaller
pipe. Welders found difficulty in obtaining sufficient penetration for a
consistent root pass. The land was extended by 0.020-in. and this allowed a
good root pass. While the smaller size pipes could be completed in just two
passes (root pass and cap pass), the 10-in. pipe required three passes.
The specifications required that the welds conform to ANSI B31.3. Qualifying
welds were subjected to tensile tests, side, root, and face bend tests, and
radiography. It was important to get a good mixture of the filler wire, which
was Monel 67 (70% copper and 30% nickel), into the root pass in order to
prevent the formation of pinholes which would disqualify the weld. The base
metal contained 88.6% copper, 10% nickel, and 1.4% iron. The greater nickel
content of the filler wire provided an increase in the tensile strength of the
weld to about 48,000 psi, compared to 44,000 psi for the base metal.
Fabrication
Copper-nickel fabrication must be protected from any contact with carbon steel,
iron, or oxides that can initiate corrosion of the copper-nickel. To meet
specifications, special clean areas were built within the shop, but isolated
from the main shop areas and dedicated to copper-nickel fabrication. These
areas were walled off with plastic panels and the air was circulated and filtered
much like cleanrooms used for high-purity industries.
Fittings, such as elbows, tees, and flanges were arranged by type and stored in
a clean storage area. Prior to welding, the oxide layer on the outside of the
pipe was removed for a distance of 2 in. from the weld joint. Special tools
such as aluminum oxide grinding wheels and stainless steel brushes were marked
with yellow paint to indicate their use on copper-nickel exclusively. Work
tables in these areas were stainless steel and all surfaces (vice jaws, pipe
stands) that might come into contact with the copper-nickel were covered to
protect the pipe from contamination.
![]() A welding head is shown installed on the copper-nickel pipe. The flange is sealed to purge the pipe internally. |
The pipe end preparation was crucial to the success of any orbital welding project. Thin walled copper-nickel pipe is prone to becoming eggshaped in storage, and it is vital that the ends be round for facing and for welding. The pipe was cut to length with a bandsaw and a Tri-Tool 206B Bevelmaster was used for the end-preparation of the two 6-in. diameter piping. A Tri-Tool 212B was used to prepare the bevels on piping from 6-12 in. diameters. The tools feature a mandrel with a Teflon pad which fits inside the pipe to make it round for machining.
The recommended end preparation for orbital welding of the pipe was a
"J" formation with a 25° bevel and a 3/32 radius, a 0.050-in. land
with a 0.030-in. extension held to very tight tolerances. In order to achieve a
consistently perfect end preparation each time, a sample coupon with an ideal
bevel for each pipe size was prepared. This model coupon was used to set the
machine tool to the bevel.
In addition, the end-preparation equipment was mounted on an adjustable stand
with casters so it could be moved into position to prep the end of the pipe without
bending or stressing. This assured an unvarying bevel and uniform preparation
necessary for repeatable, high-quality orbital welds.
Fitting end-preparation required the fitting mandrel attachment, which fit
inside the 90's and allowed it to center so the tool could make the bevel. The
large clamshell elbows had weld seams on either side which had to be ground
down on the inside (ID) so the mandrel could center. Clearly, the preparation
must be better and more consistent for orbital welding than for manual welding,
but the extra time spent in preparation is recovered during welding, and the
quality of the automatic orbital welds is far superior to manual welds.
For the copper-nickel pipe, pure argon was used for the shield gas. A mixture
of 75% argon and 25% helium was used for purging the inside of the pipe to
protect it from oxidation during welding. The gas was specially mixed in a
mixing manifold from helium stored in cylinders and the argon from the
cryogenic source.
The gas mixer is economical, and the mixed gas gives better temperature control
on the root pass, and produces welds of the highest quality. To save on gas,
special purge plugs were inserted into the pipe on either side of the weld
joint so that only a limited volume of purge gas was required to cover the weld
joint. The welders devised a system with a toy car with four-wheel drive to
pull the purge plug to the desired location inside the pipe. When the weld was
done, they pulled it out by the attached string.
Learning curve
Progress was slow at first, with over two hours required to complete one
diameter in. of weld. There was gradual improvement over the first month so
that, after 30 days, it took about 0.07 hours for an inch of weld. The average
manual welder does about 22 diameter in. per shift, while the average machine
operator does 40-50 diameter in.
The most efficient use of the orbital welding machine was achieved when it
could be operated continuously. Back-up personnel were made available for
end-preparation and pretacking of the joints to be welded orbitally so that the
welding machine operator could concentrate on the welding. Two welders
operating the orbital equipment showed far greater productivity than any of the
four manual welders. The best orbital welder completed about three times as
many diameter in. of weld in the same time period as the best manual welder. If
preparation time is factored in, it took about four hours to do a 6-in. pipe
weld manually compared to about an hour for the same weld done orbitally. The arc
time for the orbital weld was about 10-15 minutes.
Low reject rate
The use of orbital welding on copper-nickel pipe dramatically reduced the
reject rate compared to manual welding. The reject rate on the orbital welds
was about 5%, compared with 15% rejection of the copper-nickel welds done
manualIy. With the orbital equipment, the quality was obtained on the first
pass, and the welds no longer had to be cut apart and rewelded. An on-site
inspector reviewed the X-rays of the finished welded assemblies and visually
inspected the welds.
The piping was fabricated for one zone at a time and installed on the platform.
Stub-in flanges were welded onto the pipes in the shop and the flanges were
bolted together in the field to hold the system together, so no field welds
were required. Monel and grafoil, an oil-impregnated graphite material, were
used in the flange gaskets to prevent leaks.
Copper-nickel piping is part of a trend towards the use of more corrosion
resistant materials. This installation demonstrates the successful partnering
between the consumer, the contractor, and the equipment supplier.
By Alex Guiscardo, Exxon USA, Ed Dumas, Harmony Construction
and Barbara K. Henon, Ph.D., Arc Machines, Inc.
AUTHORS
Alex Guiscardo is the operations surveillance supervisor for Exxon in the Santa
Ynez Unit. He holds a BSME from the University of Texas.
Ed Dumas is project manager for Harmony Construction, Santa Paula, California.
Barbara Henon is a technical instructor of orbital tube welding for Arc
Machines. She holds a PhD in biological sciences and is vice chair of the ASME
Bioprocess Engineering Subdivision.


View our line of orbital welding equipment from Exel Systems
