Documenting Welds From An Orbital Welding Power Supply Capturing Data Electronically For Quality Assurance
Documenting Welds From An Orbital Welding Power Supply Capturing Data Electronically For Quality Assurance
Weld inspection, weld
logging, and weld recordkeeping always have been a part of quality assurance
(QA) procedures for certain industries, particularly aerospace, nuclear power,
semiconductor, and pharmaceutical.
However, in recent years the demand for logging of orbital weld records has
increased dramatically, particularly in the biopharmaceutical industry, in
which weld inspection and weld records are a significant part of the huge
amount of documentation required to achieve validation. Validation must be
complete before the U.S. Food and Drug Administration (FDA) approves a facility
for the manufacture of a new drug.
About 99 percent of the welding done at high-purity biopharmaceutical
facilities is autogenous orbital gas tungsten arc welding (GTAW). In orbital
GTAW, weld components have a square end preparation that fits snugly in an
enclosed weld head filled with inert gas. An arc is struck between a
nonconsumable tungsten electrode and the weld joint, and the electrode rotates
(orbits) around the joint to make the weld. The weld head and weld components
remain in place.
Weld Recordkeeping
If a facility is installed to the American Society of Mechanical Engineers
(ASME) Bioprocessing Equipment Standard (BPE2002), all of its welds must be
examined visually on the outside diameters (ODs) by the installer and recorded
in a weld log, and the inner diameters (IDs) of at least 20 percent of the
welds must be inspected with a borescope by an inspector representing the
owner.
Coupon logs are maintained for each sample weld to test whether the welding
equipment is properly set up and functioning. Borescope logs are maintained for
each inspected weld, weld data is etched onto the tube next to each weld, and
weld information is recorded on the isometric (ISO) drawing. Furthermore,
manufacturers of accessory equipment, such as skids, that will be installed at
the pharmaceutical plants must maintain similar weld records that become part
of the validation package.
As an example of the effort required, Donovan Engineering and Construction Co.
Inc. completed about 33,000 and 20,000 orbital welds at Wyeth Pharmaceuticals
and Lonza Biologics, respectively. At the Wyeth site, the contract called for
100 percent borescopic inspection, but out of the 32,851 welds, 850 were
"blind" welds; in other words, they were inaccessible for borescopic
inspection. The BPE standard requires that contractors have a written procedure
in place to examine blind welds.
One QA/QC inspector and one borescope technician were present for each of the
eight to 10 welding machines. The number of welding machines On-site peaked at
25 to 30 during the course of the installation, which took two years to
complete. This site had 2,116 ISO drawings, and data for each weld had to be
recorded on a particular drawing. The percentage of welds rejected for
concavity, convexity, or excessive discoloration was 0.815 percent, or 268
welds. Another 347 welds, or 1 percent, had lack of penetration, but in
accordance with BPE, they were permitted a reflow to achieve full penetration.
All of this information was recorded in a weld log. Donovan estimated that weld
inspection, documentation, testing, and commissioning comprised 15 to 20
percent of the time required to do the job.
Keeping up with Information Demand
More and more such information is collected and stored electronically.
Currently, however, weld records usually still are delivered as printouts from
the orbital welding power supply. Information on the printout is logged
manually by third-party quality assurance (QA) inspection personnel before
being converted to electronic form.
Orbital welding is not new
technology, but over the past 20 years or so, orbital welding power supplies
have evolved from digitswitch machines-on which weld parameters such as welding
current (amps), electrode travel speed in revolutions per minute, pulse times,
and level times were set on the front panel of the machine-to
microprocessorbased machines that store weld parameters as programs or
schedules in memory. With these newer machines, the operator doesn't have to
re-enter a program each time it is changed, and the power supply can print a
record that can be used for weld procedure qualification and weld logging.
The next generation of orbital welding power supplies can store the data or
upload the electronic data directly to a computer for compilation of weld
records for a particular job or for printing of QA records for manufactured
parts. Electronic data also can he printed on part labels and etched next to a
weld on the tube. At a minimum, this data would include the power supply and
weld head serial numbers, name or identification number of the welding
operator, and the date the weld was made.
Some users might want to he able to trace material heats of tubing and
fittings, purge gas certification numbers, or electrode type. In these cases,
the power supply can record project management data-such as weld identification
number, type of piping system being installed, and the building in which the
weld was made-and supply it to QA in electronic format without the need to
re-enter the data manually.
The ability to search for weld records by date, system, welding operator, or
another field can be useful to end users who might need to locate a particular
weld record quickly during an audit by the FDA or other certifying authority.
The aerospace industry has frequently required the use of chart recorders to
verify the performance of orbital welding equipment. Some new orbital welding
power supplies eliminate the need for an external chart recorder by capturing
weld data for welding current, pulsation, arc voltage and travel speed;
displaying it in real time on the power supply screen during the weld; and
showing an information chart on the screen shortly after the weld is complete.
The power supply can compare the actual data gathered during the weld and
report whether the weld parameters were performed within preset acceptance
limits.
Power Supply Limitations
It is important to understand an orbital welding power supply's limitations in
performance monitoring. When a welding power supply indicates that all
parameters have been performed as programmed, it means that the power supply
executed the instructions that were programmed. The arc continued to move
around the joint, and the amperage did not deviate significantly from the
programmed value.
If the power supply fails for some reason to execute all of the program
variables, it signals the welding operator or quality control (QC) person that
something might be wrong. For example, the power supply might fail to deliver
the programmed amperage if it's plugged into a circuit shared by other
equipment operating at the same time, or a gas fault could be triggered because
of insufficient gas flow for the weld head being used.
However, even if the power supply performs within acceptable limits, the weld
could still be defective. Any number of factors can result in an unacceptable
weld without being detected by the power supply. For example, the operator
could enter the wrong weld program or load the wrong material or material heat
or size into the weld head.
Heat-to-heat variation in stainless steel is such that a heat change may
require the operator to program a change in welding current to achieve the
right amount of penetration. Because amperage is roughly proportional to wall
thickness, loading material with the incorrect wall thickness into the weld
head could produce a weld joint with excessive or insufficient penetration.
Loading the wrong diameter for the weld program can cause the electrode in the weld
heat to travel too far or not far enough.
Failure also can occur if, for example, a welding operator with poor eyesight
or working in a dimly lit area fails to align the electrode to the weld joint.
This can create a perfectly penetrated weld that misses the joint, with all of
the penetration occurring on one side of the weld joint.
Improper ID purging is another situation the power supply might not detect.
Excessive or insufficient flow rate, as well as poor-quality purge gas with
excessive amounts of moisture or oxygen, can cause unacceptable discoloration
of the weld and heat-affected zone (HAZ). A power supply can detect gas flow to
the weld head, but an oxygen analyzer connected to the tube outlet is necessary
to determine when it is safe to start the arc. While a power supply can
indicate obvious fault conditions such as insufficient gas supply to the weld
head or stubbing out of the electrode in the weld pool, it cannot guarantee
that a good weld has been made.
Performance monitoring by a power supply can be useful in applications such as
orbital welding of semiconductor process gas lines that are not normally
inspected on the ID. This industry relies on frequent test coupon welding.
Coupon welds are done in lieu of inspection because most of the tubing is
small-diameter (0.25 to 0.50 inch OD), and inspecting the ID without damaging
the electropolished surface is difficult.
Performance monitoring is less important for industries such as the
biopharmaceutical industry, for which borescopic inspection is required on at
least 20 percent of the welds selected randomly from each separate system.
Performance monitoring cannot replace weld inspection or guarantee a good weld.
No welding machine can unequivocally detect and record the quality of a particular
weld.
Some orbital welding power supplies can, however, provide a detailed record of
each weld so that if a problem arises, tracing the problem's root cause is
simplified. The power supply's capability to download weld information directly
to a laptop computer can eliminate the need to re-enter the weld data manually
and simplifies the weld documentation process.
Barbara K Henon, Ph.D., is a contract employee at Arc
Machines Inc.
barbara.henon@arcmachines.com. The author
acknowledges helpful discussions with Gene DePierro of Pro- Tech Process Inc.
and Michael Hession of Donovan Engineering and Construction Co. Inc. in the
preparation of this article.
ASME, www.asme.org
Reprinted from the
Practical Welding Today
January / February, 2004
Applications
- Butt Welding with Filler Material
- Fixed Automation
- Narrow Groove Welding
- Socket or Fillet Welding
- Fusion Butt Welding
- 1,776 Joints Welded at Staples Center
- 316L Stainless Steel Tubing
- A Guide to Codes and Standards
- ASME BPE 2002
- ASME Compliance
- Bioprocess Piping Applications
- CBERS Propulsion System
- Christmas Tree Assemblies
- Cleanroom Fabrication
- Corrosion Resistant Materials
- Delivers Treatment Plant on Time
- Draft Beer
- Duplex Stainless Steel Tubing
- Effects of Sulfur
- Hygienic Piping System
- IBM Semiconductor Process Tools
- ID Pressurization
- Improvements in Installation
- Improving Hygienic Design
- Installation of Pharmaceutical Process Piping
- Leak-Free Tubing
- Manufacturing Facility
- Matsushita
- Orbital Welds Take Flight
- Pfizer Animal Health Group
- Pharmaceutical Piping Systems
- Plutonium-Bearing Containers
- Powdered Milk
- Purge Gas Purity
- Record Keeping and Data Aquisition
- Reducing Costs and Improving Quality
- Sanitary Process Piping
- Semiconductor Process Gas Lines
- Small Diameter Tubing
- Soldadura y tecnología del siglo XXI
- Soudage TIG orbital du système de propulsion d’un satellite
- Stainless Steel Pipe for Water Systems
- Stainless Steel Tubing
- Ultra High Purity Stainless Steel
- Vaccine Production Plant
- Weld Overlay or Cladding
- ID Welding/Cladding
- Tube-to-Tubesheet

View our line of orbital welding equipment from Exel Systems
