Installing IBM Semiconductor Process Tools at Sandia National Labs
Installing IBM Semiconductor Process Tools at Sandia National Labs
In 1992, IBM offered to give Sandia
National Laboratories (Albuquerque) 11 process tools that were then being used
for the fabrication of semiconductor devices at its T. J. Watson Research
Center in Yorktown Heights, NY. In response, Sandia established the Center for Microelectronics
Technologies (CMT) in Class 1 facilities at its Microelectronics Development
Laboratory (MDL). The project was one of the largest tool or technology
transfers that has ever taken place from industry to government (or vice
versa), involving approximately $22 million worth of equipment.
At a kickoff meeting in December 1992, the key players in the project set the
goal of removing the equipment from IBM and installing it at CMT in time to
produce a working semiconductor device by the end of 1993. The partnering
relationships that developed in the following months led to a real commitment
to the established schedule by all members of the project team. As a result,
not only was the project completed on time and an engineering success, but the
engineering management process developed was awarded one of the first Sandia
President's Quality Awards.
Fast-Track Engineering
The donated tools included a metallization cluster tool, a CVD system, two
steppers, two scanning electron microscopes, a polisher, a wet cleaner, a
coater track, and a developer track. To make room for these systems, several
tools in the Sandia fate had to be relocated. The process equipment
installation team included two local architect and engineering (AK) firms,
Smith Engineering, which was responsible for tool relocation, and Allison
Engineering, which was in charge of new tool installation. J. B. Henderson
Construction, an established Albuquerque company that had worked extensively
with Sandia at the MDL facility (formerly the radiation hardened integrated
circuit [RHIC] facility), was selected as the on-site contractor.
![]() Figure 1: A metallization cluster tool installed at Sandia's CMT. The gas lines are routed around the wafer-handlingcomponent to supply the individual modules. |
In addition to meeting technical specifications, the contractor had to be flexible with respect to expenses and yet have controls in place to avoid unnecessary cost overruns. Henderson undertook the project on a time and materials basis, which is one of the keys to fast-track, or concurrent, engineering and construction. This approach requires fewer and less-detailed drawings than conventional projects and allows more flexibility in planning. The contractor is required to give construction estimates for each segment of the job prior to beginning the work. In this case, these estimates had to be approved by the Sandia project manager, Ed Coghlan.
In addition,
meetings involving Henderson and Sandia facilities engineers and process engineers
were held weekly, during which any proposed field changes were evaluated and
the facilities personnel were alerted to possible cost overruns. A standardized
request- for- information process ensured a 24-hour response from Sandia to
problems in the field, which prevented costly delays in the installation
schedule.
William Strachan of IBM's facilities engineering staff worked closely with the
AEs, Ed Coghlan, and Jim Wernicke, the Sandia facility engineer representing
the line organization, to set the schedule and budget for each tool. IBM also
allowed personnel from Sandia and Henderson to visit the Watson Center and take
pictures of the tools in operation and provided all documentation and
engineering drawings relevant to the equipment. The availability of these data
enabled Henderson to do a considerable amount of prefabrication and site
engineering before the tools arrived in Albuquerque, thereby minimizing the
time required for the actual installation.
Installation Techniques
For applications involving hazardous gases, welding is mandated by the Uniform
Fire Code and the Uniform Building Code. The orbital welding technique used in
this project is a well-developed process suitable for installing highpurity
tubing in ultraclean facilities. The resulting welds are consistent in quality
and have a smooth inner weld bead, which prevents the entrapment of
particulates while permitting unrestricted gas flows. Two microprocessor
controlled Model 207 welding power supplies and five Model 107 digit-switch power
supplies (both Arc Machines, Pacoima, CA) were used on this job. The older
model supplies had been used to install the UHP process piping system at the
MDL (RHIC) facility at Sandia in 1984.1,2
![]() Figure 2: Piping of the main utility header supplying the sputterer. The copper lines (top) are for house nitrogen and compressed air; the stainless-steel tubing is for process gases. Isolation valves and regulators are connected with mechanical fittings, while orbital welds are used after the change in direction of the tubing. |
![]() Figure 3: Weld-test coupons cut open to expose the inner weld bead for visual inspection. Coupons are labeled by date and welder identification number. |
![]() Figure 4: Finished weld on tubing connection to the sputterer. The blue seal was used to identify a weld that had passed final leak tests. |
![]() Figure 5: Doubly contained process gas lines routed into the CVD system. All lines are clearly identified. |
The Metallization Tool. Of the
tools being installed, the sputterer raised the most difficulties with respect
to the amount and complexity of the piping and the number and difficulty of the
welds. The five cluster tool modules were installed in the center of a Class
100 area and the racks of control panels were stacked along one side of the
room. The extensive piping had to be routed in such a way that any single
module could be removed without affecting the others (see Figures 1 and 2).
A 1/2-in.-wide weld head was used for installing this tool because of the tight
clearances, and each weld was logged and marked with the welder's
identification number. Weld-test coupons were made for each change of tubing
size, change in mill heat number, and change from tubing to fitting (see Figure
3). Third-party quality control was performed by Clark Analytical
(Albuquerque): each weld was inspected visually to ensure that it met the
criteria outlined in Sandia's high-purity gas piping specifications, which
prohibit any misalignment and require full penetration. When the gas lines were
completed, each was subjected to helium leak testing. All of the process piping
was subjected to a gross test at 250 lb for 8 hours, and regulators were tested
to the rating of the lowest-rated component
Welds were inspected visually and all gas lines were subjected to helium leak testing.
in the system for a second 8-hour period. This testing was followed by tests for trace gas and particulates and final helium leak testing at 10-8 atm cm3/sec.. All lines that passed the tests were marked with blue seals (see Figure 4).
The CVD
System. Welding challenges were also
presented by the CVD system. Doubly contained process gas lines from the
facility's basement enter a valve box and feed into a cabinet with bulkhead
fitting (see Figure 5). From there, the lines run along the ceiling and then
down to a panel inside the tool. Copper tubing carries house nitrogen, which is
used for initial purging; stainless-steel tubing is used for argon, oxygen, and
nitrous oxide; and phosphine, silane, and ammonia are delivered in coaxial
lines in compliance with the Uniform Fire Code. For these coaxial lines, the
inner tubing was prepared for welding by machining the tube ends and then
joined with an autogenous fusion butt weld. When the welded assemblies had been
pressure tested for leaks, residual gas, and particles, a sleeve was moved into
place over each joint on the outer containment tube and welded in place at both
ends, as shown in Figure 6. The welded coaxial lines were then submitted to the
same pressure testing procedures as the inner process tubing.
Sandia is one of the few semiconductor facilities using all-welded coaxial lines.
Although the advantages of an all-welded system would seem obvious, many
contractors use mechanical fittings for outer containment tubing because they
feel the type of weld required is too difficult or too costly. All welded
sleeves provide the capability for vacuum monitoring of individual lines, which
can be linked to an automated facilities monitoring system. When the annular
space between the containment and process lines is held at a static vacuum of
50 µm, it is possible to detect and discriminate between leaks in the process
lines and leaks in the containment lines. This is not possible when mechanical
connections are used, because their fittings will not hold a vacuum at the
desired level for long periods of time.
Prefabrication Welding. It is
always advisable in a cleanroom installation such as this project to
prefabricate as much of the system as possible and to keep the number of field
welds, which can cause system contamination, to a minimum.
With all-welded sleeves, it is possible to detect leaks in both process and containment lines.
Sandia provided Henderson Construction with
a portable Class 100 cleanroom in the basement of the MDL facility for this
purpose. One welding power supply was placed inside the cleanroom, while a
second supply was stationed directly outside it (see Figure 7).
During the project, an average of five teams consisting of a welder and a
fitter were at work at the same time. Two welding technicians might be in the
portable cleanroom fabricating spool pieces, for example, while a field crew
installed the preassembled pieces. All team members were required to wear
cleanroom apparel in the cleanroom and to be gloved at all times, in or out of
the cleanroom.
Other Considerations. Some extra
effort on the part of the contractor and the welding equipment supplier was
required to achieve compliance with Sandia's specifications, which did not
permit any misalignment of welded components. The welding teams created special
tools for aligning tubing with the tungsten electrode in the weld heads and
used a modified vise grip to hold tubes in place during welding. Working with
the customer, the equipment supplier designed a special tube-clamp insert to
provide better tube alignment in the weld head.
![]() Figure 6: A sleeve welded to the outer coaxial tubing for the transport of hazardous gases to the CVD system. A termination fitting is shown in the foreground. |
![]() Figure 7: Welder in cleanroom apparel at orbital welding station just outside the basement cleanroom at Sandia. |
Maintaining control of incoming materials was also essential to good weldability, particularly for the containment tubing sleeve welds. Mismatches in sulfur content, especially between tubing and fittings where arc deflection can occur, had caused problems on previous Sandia installations. For this project, the sulfur contents on 1/4- to 2-in.OD and 2- to 4-in.-OD tubing were held to between 0.005 and 0.012% and 0.005 and 0.017%, respectively. Tubing extensions on valves were controlled to similar levels.
In comparison, the ASTM/ANSI specification
for 316L stainless steel permits sulfur contents of O.001 to 0.030%. Sandia is
presently keeping material in stock in order to ensure a good match in the
sulfur contents of tubing, sleeves, and other fittings.
Testing of the installed gas lines indicated that all specifications were met
or exceeded. Contaminants were measured at <10 O.1-µm particles/std cu ft,
with no particles >0.5 µm. Total hydrocarbon content and residual moisture
and oxygen levels were found acceptable, with no single impurity increased by
more than 100 ppb over the level present in the source gas.
Conclusion
Successful partnering depends on early identification of the key players and
the establishment of guidelines
defining their roles and responsibilities. During the course of this project,
weekly progress meetings were held to maintain a constant avenue of
communication and to provide a conflict resolution matrix, which enabled any
problems or potential problems to be addressed immediately. Preplanning and
site visits to IBM were also critical to the project's success, as was the use
of orbital welding for both single and coaxial process gas lines.
All of the IBM tools installed at Sandia were operational by the December 1993
target date, and since then the MDL center has established several
collaborations with private companies in which the equipment is used to
demonstrate the efficiency of new tools and processes and to foster the
development of new technologies.
Acknowledgment
Work on this project was supported by the United States Department of Energy on
Contract No. DE-AC0494AL85000.
By Barbara K. Henon, Ph.D., Arc Machines, Inc., and Ed Coghlan
Article content here.
Applications
- Butt Welding with Filler Material
- Fixed Automation
- Narrow Groove Welding
- Socket or Fillet Welding
- Fusion Butt Welding
- 1,776 Joints Welded at Staples Center
- 316L Stainless Steel Tubing
- A Guide to Codes and Standards
- ASME BPE 2002
- ASME Compliance
- Bioprocess Piping Applications
- CBERS Propulsion System
- Christmas Tree Assemblies
- Cleanroom Fabrication
- Corrosion Resistant Materials
- Delivers Treatment Plant on Time
- Draft Beer
- Duplex Stainless Steel Tubing
- Effects of Sulfur
- Hygienic Piping System
- IBM Semiconductor Process Tools
- ID Pressurization
- Improvements in Installation
- Improving Hygienic Design
- Installation of Pharmaceutical Process Piping
- Leak-Free Tubing
- Manufacturing Facility
- Matsushita
- Orbital Welds Take Flight
- Pfizer Animal Health Group
- Pharmaceutical Piping Systems
- Plutonium-Bearing Containers
- Powdered Milk
- Purge Gas Purity
- Record Keeping and Data Aquisition
- Reducing Costs and Improving Quality
- Sanitary Process Piping
- Semiconductor Process Gas Lines
- Small Diameter Tubing
- Soldadura y tecnología del siglo XXI
- Soudage TIG orbital du système de propulsion d’un satellite
- Stainless Steel Pipe for Water Systems
- Stainless Steel Tubing
- Ultra High Purity Stainless Steel
- Vaccine Production Plant
- Weld Overlay or Cladding
- ID Welding/Cladding
- Tube-to-Tubesheet








View our line of orbital welding equipment from Exel Systems
