![]() |
|||||
![]() |
|||||
|
|
|||||
| Industrial - Orbital Welding | |||||||||
When David Stine at CB&I Howe-Baker reviewed the welding requirements for a new hydrogen reformer, he knew a portion of it would be difficult if performed by conventional manual welding. Difficult material, restricted access, and limited labor created the perfect opportunity for automated orbital welding equipment to shine.
Making Decisions, Developing Procedures CB&I Howe-Baker had previous experience using orbital fusion tube welding equipment from Arc Machines, Inc. (AMI), so CBI & Howe-Baker personnel contacted AMI’s local representative, R&B Welding Applications to investigate developing welding procedures and leasing equipment for the job. Based on R&B’s recommendations, CB&I Howe-Baker selected an AMI model 227 power supply, a model 79-6625 weld head for he 5-in. tubes, and a model 79-3500 weld head for the 1-in. pipe. R&B set up the equipment in its shop and provided a week of training for Stine and four welders. Stine brought weld samples to be used for developing schedules and training the welders in using the equipment. For the 5-in. tube-to-stub welds, the procedure called for a 37-1/2 degree bevel and a 1/16-in. land. The two components were fitted together with a UNS N08810 backing ring. Because the inner portion of the tube was filled with insulating materials, it was important to penetrate the backing ring without harming the i8nsulation. The 1-in. expansion loop piping came prepared with a 37-1/2-degree bevel. The team that developed the weld procedure changed this to a J-prep for more consistent results. The weldolet end preparation was 37-1/2 degrees with a 1/16-in. land. A Georg Fischer BRB 4.5 unit was used to reprep the pipe. The J-prep had a 20-degree bevel, 1/16-in. radius, and a 0.050=in. land and extension. The tool was able to square-face and prep these pipes in one operation. Overcoming Welding Problems On-Site The first welds were on the 5-in. catalyst tubes, and the installation crew immediately ran into problems. One of the risks is that welding disturbs the microinclusions and porosities in cast material. The material sometimes blows up and gets on the tungsten and the gas lens. In manual welding, this may or may not bother the welder significantly. Automated systems with arc voltage control (AVC), such as the ones used on this job, are more sensitive to this type of problem. After a blowup the operator has to stop welding, replace the tungsten and repair or replace the gas lens, and reprep the area if necessary. Although blowups occurred far more often than anyone anticipated, the project proceeded on schedule. Of 250 welds, none were rejected in the final X-ray. The crew averaged five welds per shift, with a high of eight welds in one shift. The local weather also caused some welding problems The El Segundo, California plant is a few hundred yards from the beach. Mornings bring dew and fog, and afternoons bring wind. Any air movement faster than a few miles per hour disturbs the gas coverage and upsets the weld puddle. Excessive wind causes severe gas coverage problems and AVC instability. The crew had to erect wind barriers for every weld. The 5-in. welds near ground level were protected easily with tarpaulins and other shields. The 1-in. pipe welds were far more difficult to protect-the crew had to reduce, and in some cases eliminate, afternoon welding. These measures helped to keep rework to a minimum. Of the 1-in. pipe welds, which numbered 500, 15 rejects were identified in the final RT. This equates to a 3 percent rejection rate. Although less than 1 percent is common in automated welding, 3 percent is an acceptable rate when wind is a favor. The biggest maintenance problem was the unusually large number of gas lenses and gas cups that needed to be replaced because of the cast material problems. Even with the delays caused by blowups and prevailing weather conditions, the crew experienced relatively few delays with the automated welding process. Most of the holdups were in fit-up, tacking, waiting for backpurge, and waiting for other tradesmen. In fact, the decreased weld times made it possible to absorb these delays and still finish the project on time. Arc Machines, Inc., 10500 Orbital Way, Pacoima, CA 91331, 818-896-9556, fax 818-890-3724, www.arcmachines.com. INCONEL is a registered trademark of Huntington Alloys Inc. CB&I, One CB&I Plaza, 2103 Research Forest Drive, The Woodlands, TX 77380, 832-513-1000, www.cbi-nv.com Georg Fischer AG, Amsler-Laffon-Str. 9, 8201 Schaffhausen, Switzerland, 41-52-631-1111, www.georgfischer.com R&B Welding Applications, 21828 Lassen, Suite L., Chatsworth, CA 91311, 818-727-7972, www.rbwelding.com Reprinted from The Fabricator, August, 2005 |
|||||||||